Week 22

Despite all the torrential rain this week, our construction company, Andrew Scott, has been unbelievably busy across all areas of the new hospice site. The first section of the rotunda roof beams has been filled with concrete and the bricklayers have continued laying bricks and blocks on the Day Therapy Suite (Paul Bevan Centre).

Key milestones have also been reached on Inpatient Unit Wing 1 this week, with the completion of underground block work and a steel frame in place ready for the next stages of development. The staff car park is also taking shape with kerbs being laid.

We are all practising our sun dance hoping for better weather next week!